Wastewater Treatment Facility, Philadelphia, NY

Wastewater Treatment Facility, Philadelphia, NY

BCA worked with the Village of Philadelphia on an upgrade to the collection system, and the replacement of the WWTF with a new Sequencing Batch Reactor (SBR) Plant. To maximize funding, the $7.7M project was split into two equal phases. Total project funding included a $500,000 USDA RD Grant, $2,000,000 NYS EFC Principal Forgiveness Grant, and a $5,200,000 NYS EFC 0% Interest Loan.